Benchmarking Survey & Actions Tracker

154

Total Actions

39

Completed

113

In Progress

2

Pending

Sr # Action Detail Primary Responsibility Target Date Status Remarks
1 Resources (manpower & budget) to ensure safe and reliable plant operations to be re-evaluated. Plant Management 2026-12-31 In-progress
2 Develop Site HSEQ manual & revise OPMs & QFMs HSEQ 2026-12-31 In-progress
3 IOS committee TORs compliance and Management stewardship against HSEQ function HSEQ 2026-04-09 Completed IOS procedure rolled out and meetings are being conducted
4 Define & monitor IMS objective & KPIs in liaison with management reviews and strong record keeping & tracking of recommendations (incidents, audits, PHAs etc). HSEQ 2026-04-09 In-progress
5 Define & monitor IMS objective & KPIs in liaison with management reviews and strong record keeping & tracking of recommendations (incidents, audits, PHAs etc). Mechanical Maintenance 2026-04-09 Completed Action closed in email dated Jun 1, 2026
6 Define & monitor IMS objective & KPIs in liaison with management reviews and strong record keeping & tracking of recommendations (incidents, audits, PHAs etc). Production 2026-04-09 In-progress
7 Define & monitor IMS objective & KPIs in liaison with management reviews and strong record keeping & tracking of recommendations (incidents, audits, PHAs etc). Engineering 2026-04-09 In-progress
8 Working procedures to be developed covering job scope & responsibilities of respective personnel. HSEQ 2026-12-31 In-progress
9 Working procedures to be developed covering job scope & responsibilities of respective personnel. Mechanical Maintenance 2026-12-31 In-progress
10 Working procedures to be developed covering job scope & responsibilities of respective personnel. Production 2026-12-31 In-progress
11 Working procedures to be developed covering job scope & responsibilities of respective personnel. Engineering 2026-12-31 In-progress
12 HSEQ compliance is a line function. Accordingly, HSEQ team role to be limited to advisory / auditing function only. HSEQ 2026-12-31 Completed Approved in 1st EHSEQC meeting
13 Organograms to be revised and finalized (especially HSEQ, Inspection & Maintenance) keeping in view the required staffing and competence of all units. Plant Management 2026-12-31 In-progress
14 Technical Training Center to made functional. Plant Management 2026-10-31 Completed
15 Training Need Analysis (TNA) to be conducted and annual training calendar to be developed. Plant Management 2026-10-31 Completed
16 Study of HSEQ SOPs to be made part of training plans. HSEQ 2026-09-30 Completed Batch 64 training plan includes HSEQ related training
17 Study of HSEQ SOPs to be made part of training plans. Mechanical Maintenance 2026-09-30 In-progress
18 Study of HSEQ SOPs to be made part of training plans. Production 2026-09-30 In-progress
19 Study of HSEQ SOPs to be made part of training plans. Engineering 2026-09-30 In-progress
20 Annual firefighting training to be started for all employees. HSEQ 2026-09-30 In-progress
21 In-house Skill improvement Program (SIP) for staff and contracted manpower to be started. HSEQ 2026-10-31 In-progress
22 In-house Skill improvement Program (SIP) for staff and contracted manpower to be started. Plant Management 2026-10-31 In-progress
23 Develop & communicate JDs Admin 2026-08-31 In-progress
24 Develop & communicate JDs Mechanical Maintenance 2026-08-31 Completed
25 Develop & communicate JDs Engineering 2026-08-31 In-progress
26 Develop & communicate JDs Production 2026-08-31 In-progress
27 Develop competency matrix, implement cross-functional training, refresher programs, and job rotation for critical roles HR 2026-08-31 In-progress
28 Develop competency matrix, implement cross-functional training, refresher programs, and job rotation for critical roles Plant Management 2026-08-31 In-progress
29 Revised PTW procedure to be finalized and training & validation mechanism to be implemented. HSEQ 2026-09-30 Completed New work procedure circulated and trainings conducted
30 For confined spaces all necessary requirements (e.g. list of blinds, rescue plan, SBM, pulley arrangement for rescue etc.) to be fulfilled. HSEQ 2026-09-30 Completed Implemented
31 Work permits regular audits to be performed to ensure compliance. HSEQ 2026-09-30 Completed Audits are regularly being conducted and findings are compiled and circulated
32 Procure gas detectors and enforce testing. HSEQ 2026-09-30 Completed 02 gas detectors procured
33 Procure gas detectors and enforce testing. Production 2026-09-30 In-progress
34 LOTO procedure compliance to be strengthened HSEQ 2026-04-09 Completed Audits are being conducted regularly
35 LOTO procedure compliance to be strengthened Production 2026-04-09 Completed
36 LOTO procedure compliance to be strengthened Mechanical Maintenance 2026-04-09 Completed Being followed
37 Enforce valve tagging. HSEQ 2026-04-09 Completed Audits are being conducted regularly
38 Enforce valve tagging. Production 2026-04-09 Completed
39 Procurement of a new fire truck to planned under CAPEX-2026 to strengthen emergency response capability. HSEQ 2027-12-31 In-progress Included in Capex 2027
40 Procurement of a new fire truck to planned under CAPEX-2026 to strengthen emergency response capability. Plant Management 2027-12-31 In-progress
41 Fire truck inspection regime to be developed. HSEQ 2026-08-31 COMPLETED Completed
42 Establish fire control room. HSEQ 2028-12-31 In-progress
43 SOPs / WIs for jobs performed within fire station and rescue from height or from a vessel to be developed. HSEQ 2026-12-31 In-progress
44 Install automatic fire suppression system (e.g., FM-200 / Novec). Substation floor must be vinyl coated. E&I 2028-12-31 In-progress SR to be initiated by the respective unit
45 Power limitation for motor driven firewater pump startup to be resolved. E&I 2027-12-31 In-progress Approved in CAPEX-26
46 Install centralized fire alarm panel. E&I 2028-12-31 In-progress MOC raised in 2025 and study is in progress
47 Procedures & annual plan for all drills to be developed and compliance to be ensured. HSEQ 2026-09-30 In-progress
48 Observers to be deputed for all drills and findings to be shared and tracked regularly. HSEQ 2026-09-30 Completed Observers plan dveloped
49 Drills for safe rescue to be included in the plan. HSEQ 2026-05-31 In-progress
50 Fire scenarios to be included in the plan. HSEQ 2026-09-30 In-progress
51 Chlorine leakage handling emergency to be made part of drills HSEQ 2026-09-30 In-progress
52 ERP procedure & ERT team needs a holistic review to reduce response time. Moreover, protocol for communication with external agencies to be included in the procedure. HSEQ 2026-06-30 In-progress
53 Rescue equipment needs to be arranged and necessary rescue trainings to be conducted. HSEQ 2027-12-31 Completed 02 Tripods with winches, spine board etc arranged
54 PA system to be made functional. E&I 2027-12-31 In-progress Option of repair of existing system to be explored through local services / services from FFC-GM.
55 Medical coverage plan for off-hours to be developed. Admin 2026-12-31 Completed
56 Necessary training regarding emergency response of available medical staff (doctors & paramedics) to be conducted. HSEQ 2026-08-31 In-progress
57 01 available fully equipped ambulance to be dedicated for plant site emergencies while the other one to be utilized for local emergencies. Admin 2026-04-09 Completed
58 Incident reports recommendations tracking to be improved. HSEQ 2026-04-09 Completed Incident reports pending actions are displayed in monthly dashboard
59 Process HSEQ incidents to be investigated. HSEQ 2026-04-09 Completed 05 Process Safety incidents were investogated in 2025.
60 Incident reporting workflow to be included in the procedure. HSEQ 2026-06-30 In-progress
61 Issuance of HSEQ flash report to be started. HSEQ 2026-04-09 Completed Being followed
62 HSEQ incidents discussion to be made part of HSEQ talks. HSEQ 2026-04-09 Completed Being followed
63 HSEQ incidents discussion to be made part of HSEQ talks. Production 2026-04-09 Completed
64 HSEQ incidents discussion to be made part of HSEQ talks. Mechanical Maintenance 2026-04-09 Completed Action closed in email dated Jun 1, 2026
65 HSEQ incidents discussion to be made part of HSEQ talks. Engineering 2026-04-09 Completed
66 Train & validate incident investigators HSEQ 2027-12-31 In-progress
67 Establish internal audit regime & matrix. HSEQ 2026-12-31 In-progress
68 Employee-led BBS HSEQ 2027-12-31 In-progress
69 Develop and implement a comprehensive MOC procedure. HSEQ 2026-09-30 Completed Procedure rolled out in 2025
70 Develop and implement defeat protocol for securities as part of MOC procedure. HSEQ 2026-09-30 In-progress
71 Develop and implement defeat protocol for securities as part of MOC procedure. Production 2026-09-30 In-progress
72 Compliance of approved plan for inhibited securities to be expedited. Production 2026-04-09 In-progress
73 PHA / Risk assessments procedure to be developed and compliance to be ensured. HSEQ 2027-12-31 In-progress
74 Conduct training on PHA. HSEQ 2027-12-31 In-progress
75 Develop PHA matrix and conduct structured PHA studies. HSEQ 2027-12-31 In-progress
76 Develop PHA matrix and conduct structured PHA studies. Production 2027-12-31 In-progress
77 JSA of basic nature is conducted. It must be conducted for all non-routine jobs. Especially for confined spaces. HSEQ 2026-04-09 Completed JSA procedure implemented.
78 Revise HIRADC Procedure and enhance its awareness. HSEQ 2026-12-31 In-progress
79 Revision frequency is 04 years. It must be revised after every incident and revision frequency for all sites also needs to be reduced. HSEQ 2026-12-31 In-progress
80 Develop a standard risk matrix. HSEQ 2026-12-31 In-progress
81 HIRADC must be performed by each unit for its own activities. HSEQ only to keep record for reference. HSEQ 2026-12-31 In-progress
82 HIRADC must be performed by each unit for its own activities. HSEQ only to keep record for reference. Production 2026-12-31 In-progress
83 HIRADC must be performed by each unit for its own activities. HSEQ only to keep record for reference. Mechanical Maintenance 2026-12-31 In-progress
84 HIRADC must be performed by each unit for its own activities. HSEQ only to keep record for reference. Engineering 2026-12-31 In-progress
85 Standard practices to be used for locally fabricated geysers with steam heating system. Admin 2026-12-31 In-progress
86 Develop road map for establishing MI program Reliability 2026-12-31 In-progress
87 Implement PSV management & defeat protocol for handover. E&I 2026-05-31 Pending PSV Management Tranferred to Instrument Unit from June 15, 2026
88 Implement PSV management & defeat protocol for handover. Production 2026-05-31 In-progress
89 Implement PSV management & defeat protocol for handover. E&I 2026-05-31 In-progress Responsibility shifted to Isntrument from June 15, 2026
90 Inspection Unit should issue PSV fitness certificate only. E&I 2026-04-09 Completed Responsibility shifted to Isntrument from June 15, 2026
91 PM plan stewardship & compliance to be enforced through software tools (e.g. SAP) & regular management reviews. Mechanical Maintenance 2026-04-09 Pending Planning unit is coordinating for the PM plan compliance
92 Testing regime for tools & equipment to be developed. Mechanical Maintenance 2026-10-31 In-progress Workshop domain
93 Existing System SLD to be simplified by removal of Redundant / spare sources and parallel power flow paths. E&I 2027-12-31 In-progress Approved in CAPEX-26
94 Any modifications in system primary design to be done thru MOC only. E&I 2026-04-09 Completed
95 Revised SLD to be developed / approved in-line with AGL future generation plan. Standard scheme of 01 incomer + 01 bus coupler for each source feeder to be implemented incorporating standard HSEQ interlocks. E&I 2028-12-31 In-progress Approved in CAPEX-26
96 New type-tested switchgear with standard HSEQ interlocks for all busbars to be purchased in-line with approved SLD. E&I 2027-12-31 In-progress - No further action required post execution of interlocks in existing switchgears. - In case of technical limitations, budget to be proposed in CAPEX for procurement of new switchgear as per following plan. A (31 Dec 2030) B (31 Dec 2032) C & D (31 Dec 2034)
97 Utilization of Grid for Plant / Other Loads to be formalized thru MOC. Accordingly, extension of Busbar-C to be done (to spare old Busbar-C). E&I 2026-12-31 In-progress - Completed - Utilization of Grid for Plant / Other Loads to be formalized thru MOC. - Approved in CAPEX-26
98 Roof Repair / Waterproofing to be done for MV Switchgear Room. E&I 2027-12-31 In-progress Civil to provide estimate and propose in CAPEX-27
99 Seasonal shifting of feeders between busbars to be stopped. Any genuine requirement to be documented and formalized thru MOC. E&I 2026-12-31 Completed
100 Provision of remote control of essential breakers to be worked out in line with new SLD. E&I 2026-12-31 In-progress Wiring tracing to be executed for drawings development Third-Party / FFC-GM coordination for drawing development and standard Interlocks execution
101 As an interim measure, work instructions for switching of breakers to be developed to ensure safe switching. E&I 2026-04-09 In-progress
102 Proper cable management for cable room to be designed in line with revised SLD. E&I 2027-12-31 In-progress Approved in CAPEX-26
103 Option of engaging vendors for modifications in MV switchgear to incorporate necessary interlocks as per existing / simplified configuration to be explored. E&I 2026-12-31 In-progress
104 Replacement of LV switchgear and field distribution panels to be proposed in CAPEX (along with LV switchgear room re-modelling). E&I 2027-12-31 In-progress Budget to be proposed in CAPEX for the replacement of LV switchgears, re-modelling of LT room, and replacement of mass impregnated cables with PVC cables.
105 Replacement of cables with PVC cables to be done along with switchgear replacement. E&I 2027-12-31 In-progress Budget to be proposed in CAPEX for the replacement of LV switchgears, re-modelling of LT room, and replacement of mass impregnated cables with PVC cables.
106 Phase-wise replacement of transformers to be done. E&I 2027-12-31 In-progress Phase wise replacement plan 1) A-NG301/302 (Capex-28) 2) U-NG301/302 (Capex-29) 3) U-NG330A/331A (Capex-30) 4) U-NG330B/331B (Capex-31) 5) U-NG-217A/211A (Capex-32) 6) Y-NG 211BTR/210TR (Capex-33) 7) PS TR 1/TR 2 (Capex-34) 8) PS TR 3/TR 4 (Capex-35) 9) OCT TR A/BFW A6 TR (Capex-36) 10) OCT TR B/Admin Building TR (Cpaex-37) 11) Gen set 3 TR/WAPDA Line TR (Capex-38) 12) Banian Tree C4 TR/Y-NG 212 A TR (Capex-39) 13) Gen set 2 & 4 TR/A101BJ2-TR (Capex-40)
107 Electrical cables / plugs / switchboards to be replaced / rehabilitated. E&I 2027-12-31 In-progress No of switchboards: 40. Cables and plugs to be replaced on requirement basis. Budget to be proposed in OPEX-27.
108 Power load limitation to be resolved. E&I 2027-12-31 In-progress Approved in CAPEX-26
109 Power load limitation to be resolved. Plant Management 2027-12-31 In-progress
110 Procedures for synchronization of electrical power sources to be developed. Production 2027-12-31 In-progress Operation Uty will develop WI
111 Replacement of overhead cranes with insulated cables & rollers to be done. Mechanical Maintenance 2027-12-31 In-progress Action by Fab shop/ Machine shop
112 Functional HSEQ to be incorporated within the system. E&I 2028-12-31 In-progress
113 Gas detection system and analyzers to be rehabilitated or replaced. E&I 2028-12-31 In-progress
114 PM plans to be developed and tracked regularly. E&I 2026-08-31 In-progress
115 Develop critical instruments list with defined frequency of calibration. E&I 2026-09-30 In-progress
116 QPMs & QFMs to be revised all WP & WI to be developed, approved and controlled as per IMS protocols. Production 2027-06-30 In-progress
117 QPMs & QFMs to be revised all WP & WI to be developed, approved and controlled as per IMS protocols. Mechanical Maintenance 2027-06-30 In-progress
118 QPMs & QFMs to be revised all WP & WI to be developed, approved and controlled as per IMS protocols. Engineering 2027-06-30 In-progress
119 Plant start up, shutdown and all emergency handling procedures to be developed. Production 2026-12-31 In-progress
120 Devise a detailed plan to address mentioned housekeeping concerns of workshops. Mechanical Maintenance 2027-12-31 In-progress
121 Electrical PPEs & Chlorine Cylinder leakage handling kit to be made available. HSEQ 2027-12-31 In-progress
122 All PPE must be available near chlorine cylinder storage area. Production 2026-12-31 In-progress
123 Standard vessels to be used for storage. Engineering 2028-12-31 In-progress
124 Standard vessels to be used for storage. Reliability 2028-12-31 In-progress
125 Inspection plans to be developed and implemented. Mechanical Maintenance 2027-06-30 In-progress
126 Inspection plans to be developed and implemented. Reliability 2027-06-30 In-progress
127 For chlorine, evaluation of lime showering arrangement and switching to Nalco chlorinator system to be performed. Engineering 2028-12-31 In-progress
128 Splash rings to be installed for acid & caustic area piping. Mechanical Maintenance 2028-12-31 In-progress
129 Secondary containment to be evaluated for the tanks. Engineering 2028-12-31 In-progress
130 Secure quick lock coupling connections to be used. Mechanical Maintenance 2026-12-31 In-progress
131 Procedures & checklist to be developed for safe unloading. Production 2026-12-31 In-progress
132 Display SDS & signage. Production 2026-12-31 In-progress
133 Ensure Strict compliance of PPEs during chemical handling. Production 2026-04-09 In-progress
134 Train personnel on SDS & HAZCOM. HSEQ 2026-12-31 COMPLETED Training seesion conducted by Mr Shafqat Abbasi
135 Ensure availability of heat resistant suit. HSEQ 2027-06-30 Completed
136 Implement PSM modules in phases. HSEQ 2029-12-31 In-progress
137 Mechanism of employees’ health examination to be devised at a predefined frequency (annual of biannual etc.). HSEQ 2026-12-31 In-progress
138 Conduct periodic hygiene audits and implement food HSEQ controls. HSEQ 2026-12-31 In-progress
139 Scaffolding erection & removal Procedure to be developed with training & validation program. Mechanical Maintenance 2026-09-30 In-progress
140 Annual inspection plan of scaffolding material as well as procedure for removal / discarding of damaged material to be developed. Mechanical Maintenance 2026-09-30 In-progress
141 Third-party testing to be performed. Mechanical Maintenance 2026-12-31 Completed
142 SWL to be mention on cranes and other lifting gears. Mechanical Maintenance 2026-12-31 In-progress Workshop domain
143 Centralized Rigging plans compliance to be ensured. Mechanical Maintenance 2026-04-09 In-progress To be included in Third party audit scope
144 Contractor HSE evaluation program to be introduced as per PSM guidelines. HSEQ 2027-12-31 In-progress
145 Contractor HSEQ Manual to be developed. HSEQ 2027-12-31 In-progress
146 Implement defensive driving and site-specific driver training Admin 2026-12-31 In-progress
147 Enforce traffic rules and display speed limits, signage at appropriate locations. HSEQ 2026-12-31 In-progress
148 Develop truck driver induction and gate briefing protocol Admin 2026-12-31 Completed
149 EIA procedure and formats to be developed. HSEQ 2027-12-31 In-progress
150 Hazardous waste identification and disposal mechanisms to be developed. HSEQ 2027-06-30 In-progress
151 Environment Incident to be reported and investigated. HSEQ 2026-04-09 Completed To be followed
152 Required 3rd Party certificates & license to be acquired. HSEQ 2027-12-31 In-progress
153 Develop employee participation plan; include operators & technicians. HSEQ 2026-12-31 Completed Safety Talks, Flyers, Sharing of incident reports, Safety Audit and posters with employees
154 Formalize consultation & feedback loop HSEQ 2026-12-31 In-progress